HANDOVER SORTED - 1 year and 1 day!

Day 359 - 'pre-final' inspection day

(Fri 21/10) Had a 'pre-final' inspection this arvo. All but a few of my long defect list have been rectified. The defects still outstanding will be attended to on Monday and Tuesday next week. Final Inspection and Handover will definitely happen Wed and Thursday next week, that is of course if bloody Origin Energy fit the gas meter. They have tried twice to date and the sooks complained that the gate was locked. Get real, it's a temp fence, that is temporary, which is insecure anyway. I think they are being a little precious. Oven and rangehood looks great and so does the rest of the place. Sparkys have still forgotten some minor things which were on contract bit will fix Monday. The main thing is that WE WILL BE IN THE HOUSE NEXT WEEK :) Plenty of photos and a YouTube walk through are planned soon after. Cheers all and thanks for following my blog. It wll continue after we move in as we all know that there are still so many things to do after handover.