HANDOVER SORTED - 1 year and 1 day!

Day 62 - Retaining wall prep. cont....

Had the day off work today, so entire day was spent on site. Took forever to get started as I had a lot of visitors: neighbours, family, wife and kids etc.
Continued digging channel for wall and came across some old terracotta pipes, which were riddled with tree roots. Bloody Pittosporums will have to go now! Came across many other tree roots and debris from demolition. The last 3mt of digging was the hardest, as the clay was sodden in that area.
Finished the channel and went on with the extension of the electrical conduit which was placed in the wrong position, I had to extend it with some flex, and replace trace wire with a longer one, digging up the external pit again!
Will not be back on site until Thursday arvo (30/12) but will be then joined by the expertise of my father.
My Father in law has finished the manufacture of the posts, so all is ready to go on Thursday, fingers crossed.

Old terracotta pipes riddled with roots!

 

Trenching prep. complete



More completed trenching



More completed trenching



Conduit now extended to inside garage wall
  