Day 80 & 81 - Onsite meeting with Bricky

I turned up at 0810am and the builder was there, returned from his weekend away as he was so concerned about the issue I had raised, he wanted to be there to deal with it too. Needless to say I was impressed but also felt a bit like one of those clients builders hate.
He was also unhappy with the job and was already knocking down the wall. Bricky turned up and also saw reason for concern and was happy to re-brick that section.
I went up and bought some coffees and jam doughnuts for us to give them a chance to talk without my presence.
Bricky worked Sat & Sun to finish his job so steel support beams and further framework can be started on Mon 17/01 (Day 82)
Just got back from a sticky beak at job so far and am happy with the wall he has re-bricked. See photos.

 Re-bricked section (mortar still wet)


 Re-bricked section (mortar still wet)


Garage pillar


Rear of garage started